[19.07.2OO2] Cameco Announces Expected 2OO2 Impact of Pit Wall Failure at Kumtor Gold Mine

SASKATOON, SASKATCHEWAN, Jul 19, 2002 (CCNMatthews via COMTEX) -- Cameco Corporation previously reported the failure of a pit wall on July 8, 2002 at the Kumtor gold mine in Kyrgyzstan. A preliminary assessment of the expected impact on its 2002 mining plan and operating results has now been completed.
 
Overview
 
The rock slide involved approximately 7.5 million tonnes of rock which is expected to be removed over the next year at a projected cost of about $1 (US) per tonne. No gold reserves have been lost as a result of the rock slide as this wall failure lies entirely within the ultimate pit limit that includes another cut behind the failure zone. However, the timing of access to some high-grade ore has been altered. Cameco's 2002 net earnings are expected to be adversely impacted by approximately $35 million (Cdn).
 
Revised Mining Plan
 
Worker safety will remain of the utmost importance. On site geotechnical experts will continue to provide the company with their assessment of wall conditions and worker safety in all areas of the pit particularly around the rock slide.
 
Kumtor's gold production plan has been revised for 2002 to approximately 500,000 ounces (Cameco's share is one-third) at an average grade of 3.5 grams per tonne (g/t), a recovery rate of 77% and an estimated cash cost of about $210 (US) per ounce. This revised cash cost reflects the lower grade of the mill feed and the costs for removing the rock slide material. No allowance has been made at this time for possible proceeds from insurance.
 
Prior to the pit wall incident, the company had forecast production of 700,000 ounces at 4.9 g/t, a recovery rate of 81%, and a cash cost of $147 (US) per ounce. Mill feed remains unchanged at 5.5 million tonnes. Prior to the incident, approximately 300,000 ounces had been poured in 2002.
 
The mining plan had anticipated that work in the high-grade zone of the mine would begin this month and continue into 2003. As this zone is now partly under and exposed to the rock slide, the mill is expected to process lower grade material averaging 3.1 g/t for the remainder of 2002 when mill feed will be supplied from the stockpile and from mine production which resumed on July 15, 2002. The company's preliminary estimate is that normal operations will resume in mid-2003 with the mining of the high-grade zone.
 
The three blast hole drills covered by the slide have now been recovered. One drill will be back in service in a few days and attempts are being made to salvage one drill from parts of the remaining two.
 
Loan Payments
 
The current balance of Kumtor Gold Company's (KGC) senior debt is $77 million (US). The next principal payment of $18 million (US) plus interest, is due on December 1, 2002. Current estimates indicate that KGC will have sufficient funds to make this payment.
 
Cameco's subordinated loan to KGC currently has an outstanding balance of $65 million (US). The next expected principal payment of about $10 million (US) plus interest scheduled for December 2002 will be deferred.
 
Hedge Position
 
Cameco expects that 200,000 ounces of Kumtor's gold hedges will be rolled forward to future periods. Although this action will not have a cash impact, such redesignation of hedge contracts will have a $2 million adverse impact on Cameco's earnings. This has been included in the earnings reduction figure mentioned above.
 
Profile
 
Cameco, with its head office in Saskatoon, Saskatchewan, is the world's largest uranium supplier. The company's uranium products are used to generate electricity in nuclear energy plants around the world, providing one of the cleanest sources of energy available today. Cameco's shares trade on the Toronto and New York stock exchanges.
 
CCNMatthews, July 19, 2002